Temporary internal road

TASK

With the development of the production plant, it was necessary to create internal roads for trucks. A solution was sought, the installation of which does not require preparation of the base and will allow for temporary passage of vehicles to the loading places.

SOLUTION

Laying ROAD SYSTEM road plates directly on the ground turned out to be possible as the ground was hard and permeable. After leveling the surface, the plates were quickly installed thanks to the special design of ROAD SYSTEM LINK.

RESULT

The road was laid in a classic way, by joining the panels along the width of the strip with their longer sides, thus obtaining 3.6 m. The passage of trucks was smooth, keeping the speed limit of 10 km/h.

USED PRODUCTS

ROAD SYSTEM 200

Choose your geoPRODUCT

Go to online shop and place an order or download our catalog to get familiar with our offer. Contact us and get an offer tailored to your needs.

Store

Ważne: Strona wykorzystuje pliki cookies. W ramach naszej witryny stosujemy pliki cookies w celu świadczenia Państwu usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Państwa urządzeniu końcowym. Możecie Państwo dokonać w każdym czasie zmiany ustawień dotyczących cookies.