TASK

In terrain-challenging conditions, where high groundwater levels and difficult soil pose difficulties, the company responsible for window installation set a condition: the road near the building must be properly hardened to enable window installation. It was expected to provide a stable base for construction equipment, even in the most demanding terrain conditions.

SOLUTION

In light of future land development plans, the property owner opted for the temporary laying of plastic road panels as a driveway. This solution provides a solid surface that meets the requirements for window installation while being quick to install.

RESULT

In just two hours, a solid 40-meter driveway was created that meets all the criteria needed for window installation. This allowed the equipment to reach the site and install the windows smoothly. This fast and efficient solution facilitated the smooth progress of construction work, ensuring safety and installation efficiency, regardless of terrain difficulties.

Materials Used

ROAD SYSTEM 200

Choose your geoPRODUCT

Go to online shop and place an order or download our catalog to get familiar with our offer. Contact us and get an offer tailored to your needs.

Store

Ważne: Strona wykorzystuje pliki cookies. W ramach naszej witryny stosujemy pliki cookies w celu świadczenia Państwu usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Państwa urządzeniu końcowym. Możecie Państwo dokonać w każdym czasie zmiany ustawień dotyczących cookies.